PassLeader released the NEWEST CompTIA PK0-004 exam dumps recently! Both PK0-004 VCE dumps and PK0-004 PDF dumps are available on PassLeader, either PK0-004 VCE dumps or PK0-004 PDF dumps have the NEWEST PK0-004 exam questions in it, they will help you passing CompTIA PK0-004 exam easily! You can download the valid PK0-004 dumps VCE and PDF from PassLeader here: https://www.passleader.com/pk0-004.html (484 Q&As Dumps –> 499 Q&As Dumps –> 567 Q&As Dumps –> 596 Q&As Dumps –> 715 Q&As Dumps –> 758 Q&As Dumps –> 789 Q&As Dumps –> 1069 Q&As Dumps)

Also, previewing the NEWEST PassLeader PK0-004 dumps online for free on Google Drive: https://drive.google.com/open?id=0B-ob6L_QjGLpWmFpamxGZTNmX0U

QUESTION 41
A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?

A.    Cost, schedule, organizational chart, and risks/issues
B.    Risk/issues, cost, RAO chart, and action items
C.    Schedule, cost, risk/issues, and milestones
D.    Action items, organizational chart, schedule, and NDA

Answer: D

QUESTION 42
During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take?

A.    Alert the project sponsor of the situation.
B.    Contact the customer and request more funding.
C.    Announce the project will end early due to lack of funds.
D.    Attempt to save money in downstream activities.

Answer: D

QUESTION 43
A stakeholder is unaware of a project’s status. Which of the following documents should the project manager consult to ensure a?stakeholders are notified of project changes? (Select TWO.)

A.    Status report
B.    Organizational chart
C.    RAO matrix
D.    Meeting minutes
E.    Communication plan

Answer: AC

QUESTION 44
There are four parallel, paths on a network diagram. The summer duration d each path is below:
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?

A.    A, C, G
B.    A, B, F
C.    D, E, H
D.    D, B, F

Answer: C

QUESTION 45
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints. Which of the following documents should the project manager use to obtain this information?

A.    Project schedule
B.    Balanced scorecard
C.    Issue log
D.    Status report

Answer: A

QUESTION 46
The key stakeholders have reported the project pace as being slow The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date To alter the pace of the project, which of the following should the project manager do FIRST?

A.    Give approval for the change requested by the project sponsor
B.    Deny the request from the project sponsor
C.    Document the change request from the project sponsor
D.    Ask the project sponsor to change the request

Answer: A

QUESTION 47
A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services. Which of the following documents will the company MOST likely release-FlRST?

A.    RFO
B.    RFI
C.    RFP
D.    RFQ

Answer: A

QUESTION 48
A project manager is justifying a required change with the associated impact on the project. Which of the following is the NEXT step?

A.    Implementation
B.    Approval
C.    Validation
D.    Auditing

Answer: C


Welcome to choose PassLeader PK0-004 dumps for 100% passing CompTIA PK0-004 exam: https://www.passleader.com/pk0-004.html (484 Q&As VCE Dumps and PDF Dumps –> 499 Q&As VCE Dumps and PDF Dumps –> 567 Q&As VCE Dumps and PDF Dumps –> 596 Q&As VCE Dumps and PDF Dumps –> 715 Q&As VCE Dumps and PDF Dumps –> 758 Q&As VCE Dumps and PDF Dumps –> 789 Q&As VCE Dumps and PDF Dumps –> 1069 Q&As VCE Dumps and PDF Dumps)