PassLeader released the NEWEST CompTIA PK0-004 exam dumps recently! Both PK0-004 VCE dumps and PK0-004 PDF dumps are available on PassLeader, either PK0-004 VCE dumps or PK0-004 PDF dumps have the NEWEST PK0-004 exam questions in it, they will help you passing CompTIA PK0-004 exam easily! You can download the valid PK0-004 dumps VCE and PDF from PassLeader here: https://www.passleader.com/pk0-004.html (484 Q&As Dumps –> 499 Q&As Dumps –> 567 Q&As Dumps –> 596 Q&As Dumps –> 715 Q&As Dumps –> 758 Q&As Dumps –> 789 Q&As Dumps –> 1069 Q&As Dumps)

Also, previewing the NEWEST PassLeader PK0-004 dumps online for free on Google Drive: https://drive.google.com/open?id=0B-ob6L_QjGLpWmFpamxGZTNmX0U

QUESTION 1
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation. Which of the following should the project manager bring to the meeting to support this recommendation? (Select TWO.)

A.    The issue log to show why the vendor should be replaced
B.    The team action items to show why the vendor should be replaced
C.    The scope statement to show why the vendor should be replaced
D.    A procurement plan to show why the vendor should be replaced
E.    A change management plan to have the vendor replaced

Answer: AE

QUESTION 2
A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low high bids must be rejected to determine the selected vendor. Which of the following terms describes this requirement?

A.    Outsourcing
B.    Business acquisition
C.    Business process change
D.    Internal reorganization

Answer: A

QUESTION 3
The project manager has noticed a vendor is not performing in accordance with the SLA. Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?

A.    Balanced score card
B.    WBS
C.    Post-project evaluation
D.    PERT

Answer: B

QUESTION 4
Team members have reported that meetings are poorly attended and unproductive. Which of the following steps can the project manager take to make the meetings more productive?

A.    Discontinue the meetings with the poorest attendance.
B.    Decrease the length of the meetings.
C.    Distribute an agenda before each meeting.
D.    Document team member attendance and report it to management.

Answer: D

QUESTION 5
Which of the following documents should be used to provide high-level reporting to key stakeholders?

A.    Dashboard
B.    Communication plan
C.    Statement of work
D.    Project charter

Answer: C

QUESTION 6
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the fallowing documents would contain these items?

A.    Business case
B.    Requirements document
C.    Project timeline
D.    Task plan

Answer: A

QUESTION 7
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project’s resources before the scheduled project close- date The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team reference to fast-track the project? (Select TWO.)

A.    Scope management plan
B.    Configuration management plan
C.    Network diagram
D.    Project schedule
E.    Project plan

Answer: AC

QUESTION 8
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months. Which of the following should have occurred to prevent this issue?

A.    During the planning phase, the project manager should have recognized the relationship between the vendor’s and project team’s tasks and adjusted the schedule for the project team to begin activities two months later.
B.    The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.
C.    During the project team’s regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.
D.    During the project team’s regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.

Answer: C


Welcome to choose PassLeader PK0-004 dumps for 100% passing CompTIA PK0-004 exam: https://www.passleader.com/pk0-004.html (484 Q&As VCE Dumps and PDF Dumps –> 499 Q&As VCE Dumps and PDF Dumps –> 567 Q&As VCE Dumps and PDF Dumps –> 596 Q&As VCE Dumps and PDF Dumps –> 715 Q&As VCE Dumps and PDF Dumps –> 758 Q&As VCE Dumps and PDF Dumps –> 789 Q&As VCE Dumps and PDF Dumps –> 1069 Q&As VCE Dumps and PDF Dumps)